Time and work

  1. 1. Manav can clean a warehouse in 14 days and Jai can do it in 35 days. Working together, in how many days will they finish it?

    Options for problem 1

GA-2 · General Aptitude: analytical

Direction sense

  1. 2. Starting from home, Ravi walks 15 km north, turns right and walks 11 km, turns right again and walks 3 km, then turns left and walks 5 km. How far is he from home, and in which direction?

    Options for problem 2

EM · Engineering Mathematics

Numerical methods

  1. 3. Using the Newton–Raphson method for f(x) = x² − 5, starting from x₀ = 2, what is x₁?

    Options for problem 3

Subject · Mechanical Engineering

Manufacturing

  1. 4. A 100 mm diameter workpiece turns at 800 rpm. What is the cutting speed in m/min?

    Options for problem 4
  2. 5. A tool follows Taylor’s law VTⁿ = C with n = 0.5. It lasts 30 min at 60 m/min. How long does it last at 72 m/min?

    Options for problem 5
  3. 6. What mass of air (R = 0.287 kJ/kg·K) occupies 2 m³ at 200 kPa and 127 °C? (revision: Thermodynamics)

    Options for problem 6