tutor.org.in

CA Intermediate · Day 61 of 240

Day 61.

Choose an answer, check it, and read why each option is right or wrong.

Paper 1 · Advanced Accounting

Construction contracts

  1. 1. Under AS 7, a fixed-price contract is for ₹1,59,00,000 and total costs are expected to be ₹1,30,00,000. Costs of ₹78,00,000 have been incurred to date. Using the percentage of completion method, how much revenue is recognised to date?

    Options for problem 1
  2. 2. Under AS 28, an asset has a carrying amount of ₹21,00,000. Its net selling price is ₹18,30,000 and its value in use is ₹16,30,000. What impairment loss is recognised? (revision: Impairment of assets)

    Options for problem 2

Paper 2 · Corporate and Other Laws

Limited Liability Partnership Act, 2008

  1. 3. Which statement about an LLP is correct?

    Options for problem 3

Paper 3B · Goods and Services Tax

Goods and services tax

  1. 4. How is the import of goods into India treated under GST?

    Options for problem 4

Paper 4 · Cost and Management Accounting

Process costing

  1. 5. 6,000 kg are put into a process at a total cost of ₹3,03,600. Normal loss is 10% of input and is sold as scrap for ₹2 a kg. Output is 5,150 kg. What is the cost per kg of good output?

    Options for problem 5
  2. 6. Opening work in progress was 400 units, 20% complete for conversion. 3,500 units were started in the period; closing work in progress is 1,400 units, 50% complete for conversion. Using FIFO, how many equivalent units of conversion were produced in the period?

    Options for problem 6
  3. 7. Budgeted production overheads are ₹8,50,000 for 17,000 budgeted machine hours. In the period 19,000 machine hours were worked and actual overheads were ₹8,64,000. Were overheads under- or over-absorbed, and by how much? (revision: Overheads)

    Options for problem 7

Paper 5 · Auditing and Ethics

Going concern

  1. 8. Which is an event or condition that may cast significant doubt on an entity’s ability to continue as a going concern (SA 570)?

    Options for problem 8
  2. 9. Professional scepticism means: (revision: Audit fundamentals)

    Options for problem 9

Paper 6A · Financial Management

Leverage

  1. 10. Sales are ₹24,00,000, variable costs ₹14,40,000, fixed operating costs ₹3,80,000 and interest ₹2,32,000. What is the degree of combined leverage?

    Options for problem 10
  2. 11. The risk-free rate is 5%, the expected return on the market is 12% and a company’s equity beta is 1.25. What is its cost of equity under the capital asset pricing model? (revision: Cost of capital)

    Options for problem 11

Authored by Trisha Mallick for TUTOR’s Accounting course. © Trisha Mallick. All rights reserved.