1. Under AS 7, a fixed-price contract is for ₹82,00,000 and total costs are expected to be ₹50,00,000. Costs of ₹37,50,000 have been incurred to date. Using the percentage of completion method, how much revenue is recognised to date?
2. Under AS 16, a company borrows ₹80,00,000 at 8% a year specifically to build a qualifying asset. Construction runs for 8 months of the year, during which part of the loan, invested until needed, earns ₹90,000. What borrowing cost is capitalised for the year? (revision: Borrowing costs)
Paper 2 · Corporate and Other Laws
Limited Liability Partnership Act, 2008
3. What is the minimum number of designated partners an LLP must have?
Paper 3B · Goods and Services Tax
Goods and services tax
4. How is the import of goods into India treated under GST?
Paper 4 · Cost and Management Accounting
Budgeting
5. A semi-variable cost was ₹1,27,000 at 7,000 units and ₹1,67,000 at 12,000 units. Using the high–low method, what cost is expected at 16,000 units?
6. Which statement describes zero-based budgeting?
7. Budgeted production overheads are ₹5,10,000 for 17,000 budgeted machine hours. In the period 15,000 machine hours were worked and actual overheads were ₹4,87,000. Were overheads under- or over-absorbed, and by how much? (revision: Overheads)
Paper 5 · Auditing and Ethics
Audit sampling
8. In audit sampling (SA 530), sampling risk is the risk that:
9. Which fraud risk does SA 240 treat as present in all entities, so it cannot be rebutted? (revision: Fraud and error)
Paper 6A · Financial Management
Leverage
10. Sales are ₹38,00,000, variable costs ₹19,00,000, fixed operating costs ₹7,60,000 and interest ₹2,28,000. What is the degree of operating leverage?