tutor.org.in

GATE Mechanical Engineering (ME) · Day 66 of 300

Day 66.

Choose an answer, check it, and read why each option is right or wrong.

GA-1 · General Aptitude: quantitative

Time and work

  1. 1. Esha can harvest a field in 21 days and Kiran can do it in 42 days. Working together, in how many days will they finish it?

    Options for problem 1

GA-2 · General Aptitude: analytical

Direction sense

  1. 2. Starting from home, Ravi walks 12 km north, turns right and walks 3 km, turns right again and walks 4 km, then turns left and walks 3 km. How far is he from home, and in which direction?

    Options for problem 2

EM · Engineering Mathematics

Numerical methods

  1. 3. Using the Newton–Raphson method for f(x) = x² − 10, starting from x₀ = 2, what is x₁?

    Options for problem 3

Subject · Mechanical Engineering

Manufacturing

  1. 4. A tool follows Taylor’s law VTⁿ = C with n = 0.25. It lasts 60 min at 100 m/min. How long does it last at 125 m/min?

    Options for problem 4
  2. 5. A tool follows Taylor’s law VTⁿ = C with n = 0.25. It lasts 30 min at 100 m/min. How long does it last at 125 m/min?

    Options for problem 5
  3. 6. A plane wall 0.25 m thick with area 5 m² and conductivity 200 W/m·K has a temperature difference of 20 K across it. What is the heat flow? (revision: Heat transfer)

    Options for problem 6