GA-1 · General Aptitude: quantitative
Algebra
1. If x + 1/x = 16, what is the value of x³ + 1/x³?
GA-2 · General Aptitude: analytical
Calendars
2. Today is Monday. What day of the week will it be 394 days from today?
EM · Engineering Mathematics
Complex variables
3. If f = u + iv is analytic, which pair of equations must hold?
Subject · Electrical Engineering
Power systems
4. On a long transmission line at light load, the receiving-end voltage can exceed the sending-end voltage. This is:
5. A balanced three-phase load takes 44 A at a line voltage of 11000 V and power factor 0.9. What real power does it take, in kW?
6. x(t) = cos(2π·1700t) + sin(2π·1350t). What is its Nyquist sampling rate? (revision: Signals and systems)