GA-1 · General Aptitude: quantitative
Time and work
1. A alone can do a piece of work in 21 days and B alone in 42 days. They work together for 6 days, after which B leaves. In how many more days will A finish the work?
GA-2 · General Aptitude: analytical
Direction sense
2. Starting from home, Ravi walks 16 km north, turns left and walks 8 km, turns left again and walks 4 km, then turns right and walks 1 km. How far is he from home, and in which direction?
EM · Engineering Mathematics
Numerical methods
3. Using the trapezoidal rule with 2 equal intervals, estimate ∫ from 0 to 1 of 1/(1 + x) dx.
Subject · Electrical Engineering
Electrical machines
4. A 4-pole DC generator with a lap-wound armature of 480 conductors has 0.02 Wb per pole and runs at 1000 rpm. What EMF does it generate?
5. An ideal transformer has 1000 primary turns and 50 secondary turns. With 230 V on the primary, what is the secondary voltage?
6. A single-phase load draws 17 A (rms) from 110 V (rms) at a power factor of 0.7 lagging. What real power does it consume? (revision: Electric circuits)