Algebra

  1. 1. If x + 1/x = 14, what is the value of x² + 1/x²?

    Options for problem 1

GA-2 · General Aptitude: analytical

Calendars

  1. 2. Today is Thursday. What day of the week will it be 737 days from today?

    Options for problem 2

EM · Engineering Mathematics

Complex variables

  1. 3. What is |z₁z₂| when z₁ = 3 + 4i and z₂ = 8 + 6i?

    Options for problem 3

Subject · Civil Engineering

Surveying

  1. 4. A backsight of 1.651 m is taken on a benchmark of reduced level 150.5 m, and a foresight of 2.186 m on point P. What is the reduced level of P?

    Options for problem 4
  2. 5. What is the correction for the Earth’s curvature (alone) over a sight of 2 km, in metres?

    Options for problem 5
  3. 6. A catchment of 1 km² with runoff coefficient 0.3 receives a design rainfall intensity of 20 mm/h. What peak runoff does the rational method give? (revision: Water resources engineering)

    Options for problem 6